Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
Dec 1, 2014 28" Bomu - Bonny Pipeline at Oloma. Nov 29, 2014 Swamp Sabotage 6 Spill was contained on 29 Nov 2014, recovery completed on 02 Dec 2014, assessment completed on 18 Feb 2015, clean-up and remediation completed on 03 Jul 2015, site certified on 06 Jul 2015 - Download Download
Dec 1, 2014 28" Nkpoku - Bomu Trans Niger Pipeline Right of Way at Gio. Dec 2, 2014 Land Sabotage 6 Recovery completed on 02 Dec 2014, assessment completed on 08 Jul 2015, clean-up and remediation completed on 22 Oct 2015, site certified on 30 Jun 2016 - Download Download
Dec 3, 2014 10" Diebu Creek - Nun river Pipeline at Ekowe Dec 10, 2014 Land Sabotage 8 Spill was contained on 04 Dec 2014, recovery completed on 15 Dec 2014, assessment completed on 21 Jan 2015, clean-up and remediation completed on 10 Jul 2015, site certified on 21 Sep 2015 - Download Download
Dec 3, 2014 6" Odeama - Tora Pipeline at Nembe Bassambiri Dec 9, 2014 Swamp Sabotage 1 Spill was contained on 02 Dec 2014, no recoverable oil found, assessment completed on 14 Jan 2015, clean-up and remediation completed on 21 Sep 2015, site certified on 25 Nov 2015 - Download Download
Dec 4, 2014 20’’ Opukushi-Brass Creek at Amabulou Dec 7, 2014 Swamp Sabotage 0.6 Spill was contained on 03 Dec 2014, no recoverable oil found, assessment completed on 22 Feb 2015, clean-up and remediation completed on 27 Nov 2015, site certified on 17 May 2016 - Download Download
Dec 6, 2014 6'' Yokri Manifold - 8 Test Flowline at Yokri Dec 12, 2014 Swamp Operational 2 Spill was contained on 05 Dec 2014, no recoverable oil found, assessment completed on 06 Feb 2015, clean-up and remediation completed on 21 Apr 2017, site certification planned for July 2017 - Download Download
Dec 11, 2014 4'' Obelle - Ibaa Pipeline at Ibaa/Omueze Dec 6, 2014 Land Sabotage 3 Spill was contained on 06 Dec 2014, recovery completed on 06 Dec 2014, assessment completed on 22 Jan 2015, clean-up and remediation completed on 03 Jun 2015, site certified on 11 Aug 2015 - Download Download
Dec 15, 2014 28" Nkpoku - Bomu Pipeline at Elelenwo Dec 15, 2014 Land Sabotage 2 Spill was contained on 14 Dec 2014, no recoverable oil found, assessment completed on 23 Mar 2015, clean-up and remediation not required, site certified on 06 Jul 2015 - Download Download
Dec 16, 2014 28" Bomu-Bonny Pipeline at Bodo City Dec 18, 2014 Land Sabotage 10 No recoverable oil found, assessment completed on 25 Aug 2015, clean-up and remediation planned for January 2019 - Download Download
Dec 18, 2014 30'' Nembe Creek Pipeline at KM 45 Awoba Dec 19, 2014 Swamp Sabotage 10 No recoverable oil found, assessment completed on 19 May 2015, clean-up and remediation completed on 11 Jan 2016, site certified on 25 Feb 2016 - Download Download
Dec 23, 2014 28" Nkpoku-Bomu Pipeline at K-Dere Jan 5, 2015 Land Sabotage 31 Recovery completed on 22 Jan 2015, assessment completed on 05 Jun 2015, clean-up and remediation planned for May 2018 - Download Download
Dec 26, 2014 12" Imo River - Ogale Pipeline at Komkom Dec 27, 2014 Land Sabotage 35 Spill was contained on 27 Dec 2014, recovery completed on 30 Dec 2014, assessment completed on 16 Jan 2015, clean-up and remediation completed on 30 Apr 2016, site certified on 16 May 2016 - Download Download
Dec 31, 2014 Santa Barbara Well 14S Flowline at Nembe - Bassambiri Jan 26, 2015 Swamp Sabotage 44 No recoverable oil found, assessment completed on 11 Feb 2015, clean-up and remediation completed on 23 Oct 2015, site certification planned for April 2016 - Download Download