July 2016
Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
04.07.2016 18'' Assa-Rumuekpe Pipeline at Elele-Alimini Ihuaba 12.07.2016 Land Sabotage 264 Recovery completed on 14 Jul 2016, assessment completed on 20 Jul 2016, clean-up and remediation planned for January 2017 - Download Download
05.07.2016 Yokri Well 113T Flowline at Obotobo I & II 20.07.2016 Swamp Sabotage 9 Recovery planned for August 2016 - Download Download
07.07.2016 16" Zarama - Gbaran CPF Bulkline at Okotiama 13.07.2016 Swamp Sabotage 0.9 Spill was contained on 06 Jul 2016, recovery completed on 07 Jul 2016, assessment planned for November 2016 - Download Download
09.07.2016 16'' Tunu-Brass Creek Pipeline Riser at Peretorugbene 19.07.2016 Swamp Sabotage 94 Recovery completed on 11 Oct 2016, assessment planned for November 2016 - Download Download
11.07.2016 28'' Nkpoku - Bomu Pipeline at Gio - Kporghor 12.07.2016 Land Sabotage 294 Recovery completed on 01 Aug 2016, assessment planned for December 2016 - Download Download
14.07.2016 Ahia Well 3S Flowline at Egbeda 19.07.2016 Land Sabotage 0.1 No recoverable oil found, assessment completed on 11 Aug 2016, clean-up and remediation planned for January 2017 - Download Download
16.07.2016 Obigbo North Well 26T_18S_20T_Three_disused Flowlines at Umuwalia 21.07.2016 Land Other 0.1 No recoverable oil found, assessment completed on 10 Aug 2016, clean-up and remediation planned for November 2016 - Download Download
21.07.2016 16" Egbema - Assa Pipeline at Obile. 18.08.2016 Land Sabotage 2 No recoverable oil found, assessment completed on 07 Oct 2016, clean-up and remediation planned for December 2016 - Download Download
22.07.2016 12'' Imo River 2 – Ogale Pipeline at Umuedeokwara 28.07.2016 Land Sabotage 14 Recovery completed on 11 Aug 2016, assessment completed on 26 Aug 2016, clean-up and remediation planned for December 2016 - Download Download
31.07.2016 24" Trans Ramos Pipeline at Odimodi 22.09.2016 Swamp Sabotage 417 Recovery completed on 03 Oct 2016, assessment completed on 08 Oct 2016, clean-up and remediation planned for January 2017 This JIV report records the spill volume and extent of impact from two spills incidents on the 24” Trans Ramos Pipeline at Odimodi one on the 31st July 2016 and the other on 13th August 2016 as it was not possible to differentiate the volume and impact separately. Please refer to the incident from 13th August at the 24” Trans Ramos Pipeline at Odimodi (also published on the spills data website) for further information. N/A N/A