Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
Sep 03, 2018 24” Nkpoku-Bomu Pipeline at Bera. Sep 05, 2018 Land Sabotage 19 Spill was contained on 04 Sep 2018, recovery planned for September 2018 - Download Download
Sep 04, 2018 Imo River2 Well 31L Flowline at Odagwa-Umuadeokwara Sep 06, 2018 Land Sabotage 0.1 No recoverable oil found, assessment planned to be completed on November 2018 - Download Download
Sep 06, 2018 Forcados Terminal Single Point Mooring (SPM)2 at Ogulagha Kingdom Sep 12, 2018 Water Sabotage 2 No recoverable oil found, assessment planned for November 2018 The incident occurred on 5th September 2018. JIV commenced on 12th September 2018 but the cause of spill could not be identified due to difficulty encountered in the process. JIV was then recommenced and concluded on 15th October 2018 Download Download
Sep 06, 2018 14" Okordia-Rumuekpe Pipeline at Akaramini Sep 07, 2018 Land Sabotage 81 Spill was contained on 07 Sep 2018, recovery planned to be completed on October 2018 - Download Download
Sep 08, 2018 20" Otumara - Escravos Pipeline at Ugboegungun Sep 09, 2018 Swamp Sabotage 172 Recovery planned to be completed on October 2018 - Download Download
Sep 08, 2018 4'' Diebu Creek Closed Drain Vessel Flange at Peremabiri Sep 25, 2018 Land Operational 0.01 No recoverable oil found, assessment planned for November 2018 - Download Download
Sep 09, 2018 36" Nkpoku - Bomu Pipeline at Rumuesara Eneka Sep 11, 2018 Land Sabotage 622 Recovery planned to be completed on October 2018 - Download Download
Sep 11, 2018 Imo River Well 59T Flowline at Igiriukwu_Owaza Sep 15, 2018 Land Sabotage 0.2 No recoverable oil found, assessment planned to be completed on November 2018 - Download Download
Sep 14, 2018 6'' Obigbo North - Ogale Pipeline at Ogale Sep 15, 2018 Land Sabotage 72 Spill was contained on 04 Sep 2018, recovery completed on 21 Sep 2018, assessment planned for October 2018 - Download Download
Sep 15, 2018 16'' Egbema - Assa Rumuekpe Pipeline at Assa Sep 17, 2018 Land Sabotage 34 Recovery completed on 19 Sep 2018, assessment planned for October 2018 - Download Download
Sep 25, 2018 18" Assa - Rumuekpe Pipeline at Akpabu Sep 26, 2018 Land Sabotage 61 Recovery planned to be completed on October 2018 Recovery of free phase crude oil commenced on 26th September 2018 and planned to be completed 31st October 2018. Download Download
Sep 27, 2018 20'' Kolocreek - Rumuekpe Pipeline at Odau Sep 29, 2018 Land Sabotage 23 Recovery planned to be completed on October 2018 Recovery of free phase crude oil commenced on 27th September 2018 and planned to be completed 31st October 2018. Download Download