Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Clean-up Status Comments Photo JIV Report *
3-May-11 24" Alakiri-Bonny GPHSL at Creek 6 and Kalibiama 8-May-11 Swamp Sabotage / Theft 0.1 No recoverable oil was found on site. Cleanup of residual impacted area completed on 8th July 2011. The JIV spanned 2 days, 7th and 8th May 2011 covering two points at Creek 6 and Kalibiama. In both cases, the pipeline had been subjected to mechanical grinding, resulting in severe loss of wall thickness and failure during operational hydro testing. Post Cleanup Inspection completed on 7th October 2011. PDF PDF
6-May-11 18" Assa - Rumuekpe Pipeline at Egbeda 8-May-11 Land Sabotage / Theft 5 Recovery of spilled volume completed on 9th May 2011. Cleanup of residual impacted area completed on 8th July 2011. Post Cleanup Inspection completed on 21st July 2011. PDF PDF
8-May-11 Apara Well 3 Location at Apara. 10-May-11 Land Sabotage / Theft 1.5 Recovery of spilled oil completed on 10th May 2011. Freedom to Operate (FTO) granted by Apara community and cleanup of residual impacted area was completed on 28th June 2011. Post Cleanup Inspection completed on 13th July 2011. PDF PDF
9-May-11 10" Ekulama 1 Pipeline at Free Town 12-May-11 Swamp / Water Operational 150 Recovery of spilled volume commenced on 12th May 2011 and was completed on 18th May 2011. Cleanup of residual impacted area commenced on 15th September 2011 and was completed on 29th October 2011. Delay in the clean up of residual impacted areas was due to issues on community contracting. Post cleanup inspection completed on 3rd November 2011. PDF PDF
11-May-11 12" Imo River Pipeline at Owaza 12-May-11 Land Sabotage / Theft 26.5 Recovery of spilled volume completed on 13th May 2011. Cleanup of residual impacted area commenced on 16th May 2011 and was completed on 18th May 2011. Post Cleanup Inspection completed on 10th June 2011. PDF PDF
11-May-11 10" Diebu Creek - Nun River Pipeline at Onyioma 18-May-11 Swamp Sabotage / Theft 197.1 Recovery of spilled volume commenced on 23rd May 2011 and was completed on 28th July 2011. Clean up of residual impacted area completed on 19th September 2011. Recovery took longer than envisaged due to the difficult terrain, rainy season and increased work scope. Initial volume of spill estimated during JIV of 18th May 2011 was 119.6 bbls. However, 138 bbls of oil was subsequently recovered, resulting in a restated volume of 197.1 bbls. Restated volume has been communicated to the Regulators as per statutory requirement. Post Cleanup Inspection completed on 27th March 2012. PDF PDF
13-May-11 36" Rumuekpe - Nkpoku Pipeline at Rumuekpe 14-May-11 Land Sabotage / Theft 7 Recovery of spilled volume completed on 14th May 2011. Cleanup of residual impacted area completed on 4th June 2011. Post Cleanup Inspection completed on 10th June 2011. PDF PDF
15-May-11 Awoba North West Well1 L/S Flowline at Awoba 19-May-11 Swamp Operational 10 No recoverable oil was found on site due to tidal overflow. Clean up of residual impacted area completed on 22nd July 2011. Post Cleanup inspection completed on 10th August 2011. PDF PDF
16-May-11 18" Assa - Rumuekpe Pipeline @ Egbeda 17-May-11 Land Sabotage / Theft 2.6 Recovery of spilled volume completed on 17th May 2011. Cleanup of residual impacted area completed on 9th July 2011. Post Cleanup Inspection completed on 20th July 2011. PDF PDF
16-May-11 Cawthorne Channel Well 29T Flowline at Cawthorne Channel 18-May-11 Swamp
Operational 2.4 No recoverable oil was found on site. Cleanup of residual impacted area completed on 13th July 2011. Post Cleanup Inspection completed on 5th August 2011. PDF PDF
18-May-11 6" Awoba Pipeline at Awoba 19-May-11 Swamp Operational 0.001 No recoverable oil was found on site. No cleanup required. Post Cleanup inspection completed on 10th August 2011. PDF PDF
18-May-11 Nembe Well 20L at Nembe Creek 24-May-11 Swamp Operational 22 No recoverable oil was found on site due to tidal overflow. Cleanup of residual impacted area completed on 16th October 2011. Overall schedule considers community contracting, onset of the rainy season and difficulty of work terrain. Post Cleanup Inspection completed on 3rd November 2011. PDF PDF
25-May-11 Bonny Well 12S Flowline 15-Jun-11 Swamp Sabotage / Theft 1 No recoverable oil was found on site. Cleanup of residual impacted area completed on 27th July 2011. Minor leak (bubbles) was detected during re-start of the well. Well was immediately shut in. Initial two attempts at JIV (26th May and 13th June 2011) could not access the leak point. JIV finally completed on 15th June 2011. Post Cleanup inspection completed on 26th September 2011. Delay to completion of inspection due to logistic challenges in the area. PDF PDF