July 2011
Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Clean-up Status Comments Photo JIV Report *
3-Jul-11 Ubie Well 4S Flowline at Ubie 7-Jul-11 Land Sabotage / Theft 1 No recoverable oil was found on site. Cleanup of residual impacted area completed on 30th August 2011. Post Cleanup inspection completed on 15th November 2011. Download Photo Download JIV Report
7-Jul-11 Etelebou Well 8T Flowline at Ogboloma 12-Jul-11 Land Operational 4.05 Recovery of spilled volume and cleanup of residual impacted area commenced on 12th July and completed on 27th July 2011. The original JIV could not determine the cause of spill as the spill point was flooded at the time of visit and needed to be exposed to permit visual inspection. A repeat JIV on 9th August 2011 established that the spill was due to impact on the flowline from a third party heavy equipment working in the area. Post Cleanup inspection completed on 24th November 2011. PDF PDF
7-Jul-11 Otumara Well 22L Flowline at Otumara 18-Jul-11 Swamp Operational 21.99 No recoverable oil was found on site. Spill impact observed as oil sheen on water and stains on vegetation. Cleanup of residual impacted area completed on 14th October 2011. JIV was originally planned for the 12th July 2011 but was aborted due to community issues regarding communication of planned JIV; re-scheduled for 15th July 2011 but was also cancelled due to weather conditions . JIV finally commenced on 18th July 2011 and was concluded on 19th July 2011. Post Cleanup inspection completed on 24th October 2011. PDF PDF
8-Jul-11 Awoba Well 2T Flowline Riser at Awoba 12-Jul-11 Swamp Operational 0.13 No recoverable oil was found on site. No residual impact. JIV recommends no cleanup action required. Cleanup process closed. PDF PDF
9-Jul-11 Cawthorne Channel Well 29T Flowline at Cawthorne Channel 18-Jul-11 Swamp Operational 6.97 No recoverable oil was found on site JIV recommends no cleanup action required. Closed. PDF PDF
15-Jul-11 10'' Ogini-Eriemu delivery line at Ogini 15-Jul-11 Land Sabotage / Theft 0.14 No recoverable oil was found on site Incident involved an illegally welded 2" valve. JIV recommends no further cleanup action required. Closed. PDF PDF
16-Jul-11 Cawthorne Channel Well 24T FL ROW at Cawthorne Channel 18-Jul-11 Swamp Operational 0.9 No recoverable oil was found on site JIV recommends no cleanup action required. Closed. PDF PDF
18-Jul-11 Chokota Gathering Manifold, Igbo Etche, Obigbo 19-Jul-11 Land Sabotage / Theft 26.7 Recovery of spilled volume commenced on 18th July and completed on 29th July 2011. Cleanup of residual impacted area completed on 31st August 2011. Post Cleanup inspection completed on 21st October 2011. PDF PDF
18-Jul-11 Imo River Well 59T Flowline at Igiriukwu 20-Jul-11 Land Sabotage / Theft 4.62 No recoverable oil was found on site. Cleanup of residual impacted area completed on 12th October 2011. Delay in the cleanup of residual impacted areas was due to site flooding as a result of heavy rains. Post Cleanup inspection completed on 30th November 2011. PDF PDF
19-Jul-11 10'' Utorogu-Ughelli Pumping Station Pipeline at Otu-Jeremi 19-Jul-11 Land Operational 0.05 No recoverable oil was found on site Incident involved a failed 10" clamp. JIV recommends no further cleanup action required. Closed. PDF PDF
19-Jul-11 4" Obele pipeline at Ibaa 21-Jul-11 Land Sabotage / Theft 2.5 No recoverable oil was found on site. Cleanup of residual impacted area completed on 27th July 2011. Post Cleanup inspection completed on 25th October 2011. Delay due to community issues which were resolved on 2nd October 2011. PDF PDF
19-Jul-11 Awoba Well 5 L Flowline ROW at Awoba 22-Jul-11 Swamp Operational 2.6 No recoverable oil was found on site. Cleanup of residual impacted area completed on 3rd August 2011. Post Cleanup Inspection completed on 10th August 2011. PDF PDF
21-Jul-11 20''Ughelli Pumping Station -Warri Refinery Pipeline at Ekpan 21-Jul-11 Land Sabotage / Theft 6.85 Recovery of spilled volume completed on 29th July 2011. Cleanup of residual impacted area completed on 17th August 2011. Post Cleanup Inspection completed on 8th September 2011. PDF PDF
25-Jul-11 10" Pipeline at Ekulama 27-Jul-11 Swamp Operational 229 Recovery completed on the 8th of August 2011. Cleanup of residual impacted area completed on 29th October 2011. Post Cleanup Inspection completed on 4th November 2011. PDF PDF
31-Jul-11 Cawthorne Channel Well 21L ROW at Mbiama 3-Aug-11 Swamp Operational 0.93 No recoverable oil was found on site. Cleanup of residual impacted area commenced on 20th October 2011 and was completed on 30th October 2011. Overall schedule for cleanup considered community contracting and difficulty of the work terrain, particularly during the rains. Post Cleanup Inspection completed on 24th November 2011. PDF PDF