December 2018
Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Recovered Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
Dec 09, 2018 20" Kolo Creek to Rumuekpe Pipeline at Oruma Dec 12, 2018 Land Sabotage 344 161.5 Spill was contained on 10 Dec 2018, recovery completed on 27 Jan 2019, assessment completed on 16 Apr 2019, clean-up and remediation completed on 16 Jul 2019, site certified on 10 Oct 2019, documentation completed on 21 May 2020 - Download Download
Dec 09, 2018 6" Mininta to Ahia Bulkline at Akpabu Dec 11, 2018 Land Sabotage 11 n/a No recoverable oil found, assessment completed on 13 Jan 2019, clean-up and remediation not required, site certified on 14 Oct 2019, documentation completed on 05 Oct 2021 - Download Download
Dec 11, 2018 14" Okordia to Rumuekpe Pipeline at Ula-Ikata Dec 13, 2018 Land Sabotage 22 38 Spill was contained on 12 Dec 2018, recovery completed on 03 Feb 2019, assessment completed on 24 Mar 2019, clean-up and remediation completed on 07 Apr 2022, site certified on 17 Oct 2022, documentation completed on 21 Oct 2022 - Download Download
Dec 11, 2018 20" Otumara to Escravos Pipeline at Otumara Dec 13, 2018 Swamp Sabotage 107 150 Recovery completed on 16 Dec 2018, assessment completed on 29 Mar 2019, clean-up and remediation completed on 22 May 2019, site certified on 29 Feb 2020, documentation planned to be completed in Sep 2021 - Download Download
Dec 21, 2018 OGBOTOBO WELL 5T WELL HEAD Jan 05, 2019 Swamp Sabotage 0.4 n/a No recoverable oil found, assessment completed on 26 May 2021, clean-up and remediation not required, site certified on 22 Feb 2022, documentation completed on 09 Mar 2022 The incident occurred on 20th December 2018. JIV could not commence on 3rd January 2019 as scheduled, as the JIV Team could not be Flown to the Spill Site as a result of Poor weather condition. JIV finally commenced on 5th January 2019 and was completed same day. Download Download
Dec 23, 2018 18" Assa to Rumuekpe Pipeline at Awara-Ochia Dec 26, 2018 Land Sabotage 12 6 Recovery completed on 28 Dec 2018, assessment completed on 30 May 2019, clean-up and remediation completed on 18 Oct 2019, site certified on 28 Aug 2020, documentation completed on 28 Aug 2020 - Download Download
Dec 23, 2018 36" Rumuekpe to Nkpoku Pipeline at Ogbodo-Isiokpo Dec 24, 2018 Land Sabotage 15 6.2 Recovery completed on 31 Dec 2018, assessment completed on 21 May 2019, clean-up and remediation completed on 06 Mar 2020, site certified on 10 May 2022, documentation completed on 22 Jul 2022 - Download Download
Dec 23, 2018 8" Nkali to Imo River Pipeline at Odagwa Dec 28, 2018 Land Sabotage 6 n/a Spill was contained on 12 Dec 2018, no recoverable oil found, assessment completed on 14 May 2019, clean-up and remediation completed on 04 Jul 2019, site certified on 14 Oct 2019, documentation completed on 05 Oct 2021 - Download Download
Dec 26, 2018 12" Imo River to Ogale Pipeline at Owaza Dec 28, 2018 Land Sabotage 10 1 Spill was contained on 27 Dec 2018, recovery completed on 28 Dec 2018, assessment completed on 07 Feb 2019, clean-up and remediation not required, site certified on 26 Jul 2019, documentation planned to be completed in Sep 2021 - Download Download
Dec 28, 2018 16" Egbema to Assa Pipeline at Umudike Dec 30, 2018 Land Sabotage 0.2 n/a No recoverable oil found, assessment completed on 26 Feb 2019, clean-up and remediation completed on 25 Mar 2019, site certified on 07 Aug 2019, documentation completed on 21 May 2020 - Download Download