June 2019
Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Recovered Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
Jun 03, 2019 12" Imo River2 - Ogale Pipeline at Owaza Jun 04, 2019 Land Sabotage 40 30 Recovery completed on 16 Sep 2019, assessment completed on 08 Feb 2020, clean-up and remediation completed on 29 Jun 2021, site certification planned to be completed in Sep 2023 - Download Download
Jun 03, 2019 36" Nkpoku - Ogale Pipeline at Rumuesara-Eneka Jun 05, 2019 Land Sabotage 7 5 Recovery completed on 05 Jun 2019, assessment completed on 28 Jun 2019, clean-up and remediation completed on 15 Jan 2021, site certified on 15 Jul 2021, documentation completed on 12 May 2023 - Download Download
Jun 03, 2019 8" Nkali - Imo River2 Pipeline at Odagwa Jun 06, 2019 Land Sabotage 2 n/a No recoverable oil found, assessment completed on 02 Aug 2019, clean-up and remediation completed on 15 Mar 2021, site certified on 18 Mar 2022, documentation planned to be completed in Apr 2022 - Download Download
Jun 03, 2019 18" Assa - Rumuekpe Pipeline at Egbeda Jun 04, 2019 Land Sabotage 69 58 Recovery completed on 06 Jun 2019, assessment completed on 25 Apr 2020, clean-up and remediation completed on 25 Apr 2021, site certified on 15 Jul 2021, documentation completed on 07 Jul 2023 - Download Download
Jun 05, 2019 8" Obigbo North - New Elelenwa Pipeline at Umusonya Jun 08, 2019 Land Sabotage 6 3 Recovery completed on 09 Jun 2019, assessment completed on 25 Jul 2019, clean-up and remediation not required, site certified on 28 Aug 2020, documentation completed on 26 Mar 2021 - Download Download
Jun 05, 2019 14" Okordia - Rumuekpe Pipeline at Oshika Jun 07, 2019 Land Sabotage 81 4 Spill was contained on 06 Jun 2019, recovery completed on 16 Jan 2020, assessment completed on 15 May 2023, clean-up and remediation not required, site certification planned to be completed in Sep 2023 - Download Download
Jun 05, 2019 12" Imo River - Ogale Pipeline at Uzuaku Jun 06, 2019 Land Sabotage 13 5 Recovery completed on 08 Jun 2019, assessment completed on 24 Sep 2019, clean-up and remediation completed on 28 Jun 2020, site certified on 21 Dec 2022, documentation completed on 07 Jul 2023 - Download Download
Jun 07, 2019 4" Obelle - Ibaa Pipeline at Ibaa Jun 14, 2019 Land Sabotage 4 0.25 Recovery completed on 08 Aug 2019, assessment completed on 05 Feb 2020, clean-up and remediation completed on 24 Mar 2021, site certified on 18 Mar 2022, documentation planned to be completed in Apr 2022 - Download Download
Jun 07, 2019 36" Nkpoku - Ogale Pipeline at Rumuowha-Eneka Jun 08, 2019 Land Sabotage 0.7 n/a Spill was contained on 06 Jun 2019, no recoverable oil found, assessment completed on 28 Jun 2019, clean-up and remediation not required, site certified on 25 Nov 2019, documentation completed on 07 Jul 2023 - Download Download
Jun 09, 2019 14" Okordia - Rumuekpe Pipeline at Akara-Olu Jun 10, 2019 Land Sabotage 4 n/a No recoverable oil found, assessment completed on 13 Aug 2019, clean-up and remediation not required, site certified on 09 Mar 2020, documentation completed on 04 Oct 2021 - Download Download
Jun 10, 2019 18"Assa - Rumuekpe Pipeline at Awarra Jun 12, 2019 Land Sabotage 828 773 Recovery completed on 18 Jun 2019, assessment completed on 26 Sep 2022, clean-up and remediation not required, site certification planned to be completed in Dec 2022 - Download Download
Jun 10, 2019 14" Okordia - Rumuekpe Pipeline at Akara-Olu Jun 11, 2019 Land Sabotage 0.1 n/a No recoverable oil found, assessment completed on 11 Jun 2019, clean-up and remediation not required, site certified on 03 Oct 2019, documentation planned to be completed in Oct 2021 - Download Download
Jun 11, 2019 14" Okordia - Rumuekpe Pipeline at Akara-Olu Jun 11, 2019 Land Sabotage 0.1 n/a No recoverable oil found, assessment completed on 06 Dec 2019, clean-up and remediation not required, site certified on 07 May 2021, documentation completed on 31 Dec 2021 - Download Download
Jun 13, 2019 14" Okordia - Rumuekpe TL at Akara-Olu Jun 14, 2019 Land Sabotage 0.1 n/a No recoverable oil found, assessment completed on 10 Aug 2019, clean-up and remediation not required, site certified on 17 Oct 2022, documentation completed on 21 Oct 2022 - Download Download
Jun 13, 2019 14" Okordia - Rumuekpe Pipeline at Oshie Jun 17, 2019 Land Sabotage 0.1 n/a No recoverable oil found, assessment completed on 09 Jul 2019, clean-up and remediation not required, site certification planned to be completed in Dec 2023 - Download Download
Jun 14, 2019 18" Assa - Rumuekpe Pipeline at Awarra Jun 15, 2019 Land Sabotage 1 n/a No recoverable oil found, assessment completed on 26 Sep 2022, clean-up and remediation not required, site certification planned to be completed in Dec 2022 - Download Download
Jun 17, 2019 20" KCTL RoW at KM19 Odau Jun 23, 2019 Land Sabotage 267 1162 Spill was contained on 18 Jun 2019, recovery completed on 19 Oct 2019, assessment completed on 06 Sep 2022, clean-up and remediation not required, site certification planned to be completed in Sep 2023 - Download Download
Jun 19, 2019 24" Ogale - Bomu Pipeline at Agbeta Jun 21, 2019 Land Sabotage 0.4 n/a No recoverable oil found, assessment completed on 03 Jul 2019, clean-up and remediation completed on 25 Aug 2022, site certified on 17 Oct 2022, documentation completed on 11 Nov 2022 - Download Download
Jun 19, 2019 24" Nkpoku - Bomu Pipeline at Egbalor Jun 20, 2019 Land Sabotage 2 n/a No recoverable oil found, assessment completed on 04 Jul 2019, clean-up and remediation completed on 24 Feb 2020, site certified on 21 Dec 2020, documentation completed on 01 Feb 2021 Multiple incidents 2019_2327455, 2019_2377214 and 2019_2429471 recorded at the location. Download Download
Jun 20, 2019 12" Imo River - Ogale Pipeline at Owaza Jun 22, 2019 Land Sabotage 5 n/a No recoverable oil found, assessment completed on 17 Dec 2019, clean-up and remediation completed on 15 Nov 2021, site certification planned to be completed in Sep 2023 - Download Download
Jun 24, 2019 24'' Nkpoku - Bomu Pipeline at Sime Jun 24, 2019 Land Sabotage 38 n/a Recovery completed on 13 Jul 2019, assessment completed on 21 Apr 2021, clean-up and remediation not required, site certified on 07 May 2021, documentation completed on 21 Jan 2022 - Download Download
Jun 25, 2019 14'' Okordia -Rumuekpe Pipeline at Oshie Jun 27, 2019 Land Sabotage 227 n/a Recovery completed on 27 Aug 2019, assessment completed on 24 Jan 2020, clean-up and remediation not required, site certification planned to be completed in Sep 2023 - Download Download
Jun 25, 2019 28" Nkpoku - Bomu Pipeline at Ejama - Ebubu Jun 27, 2019 Land Sabotage 244 n/a Spill was contained on 26 Jun 2019, recovery completed on 27 Jun 2019, assessment completed on 26 Oct 2020, clean-up and remediation completed on 09 Jun 2021, site certified on 26 Nov 2021, documentation completed on 28 Feb 2022 New spill recorded at same location with ID# 2443760 on 31 Aug 2019. Download Download
Jun 29, 2019 14"Okordia to Rumuekpe pipeline at Edeoha Jul 02, 2019 Land Sabotage 2 n/a Recovery completed on 02 Jul 2019, assessment completed on 24 Jan 2020, clean-up and remediation not required, site certified on 07 May 2021, documentation completed on 05 Oct 2021 - Download Download