July 2013
Spills data for July 2013
All download files are in PDF format and opens in a new window.
Date Reported | Incident Site | JIV Date | Terrain | Cause | Estimated Spill Volume (bbl) | Recovered Spill Volume (bbl) | Clean-up Status | Comments | Photo | JIV Report |
---|---|---|---|---|---|---|---|---|---|---|
Jul 01, 2013 | Imo River Well 22S Flowline at Igiriukwu | Jul 03, 2013 | Land | Sabotage | 112 | n/a | Recovery completed on 21 Aug 2013, assessment completed on 09 Jan 2014, clean-up and remediation completed on 22 Apr 2014, site certified on 30 Aug 2014 | - | Download | Download |
Jul 03, 2013 | 6" Obigbo North _Ogale Pipeline at Ogale | Jul 05, 2013 | Land | Sabotage | 3 | n/a | Recovery completed on 05 Jul 2013, assessment completed on 14 Aug 2013, clean-up and remediation completed on 01 Nov 2013, site certified on 10 Dec 2013 | - | Download | Download |
Jul 04, 2013 | 20" Otumara to Escravos Trunkline at Otumara | Jul 06, 2013 | Swamp | Sabotage | 3 | n/a | Spill was contained on 02 Jul 2013, recovery completed on 01 Aug 2013, assessment completed on 09 Oct 2013, clean-up and remediation completed on 14 Mar 2014, site certified on 16 May 2014 | - | Download | Download |
Jul 05, 2013 | 24'' Nkpoku to Bomu TNP at Rumuowegwu/Eneka | Jul 10, 2013 | Land | Sabotage | 6 | n/a | No recoverable oil found, assessment completed on 12 Sep 2013, clean-up and remediation completed on 28 Oct 2013, site certified on 09 Dec 2013 | - | Download | Download |
Jul 09, 2013 | 12" Adibawa - Okordia DL at Ikarama (old line) | Jul 19, 2013 | Land | Sabotage | 1.8 | n/a | Spill was contained on 05 Jul 2013, no recoverable oil found, assessment completed on 18 Sep 2013, clean-up and remediation completed on 18 Sep 2013, site certified on 30 Oct 2013 | Incident involved two leak points in close proximity | Download | Download |
Jul 10, 2013 | 20" Rumuekpe to Nkpoku Pipeline at Ibaa | Jul 12, 2013 | Land | Sabotage | 1070 | n/a | Spill was contained on 11 Jul 2013, recovery completed on 30 Aug 2013, assessment completed on 02 Sep 2013, clean-up and remediation completed on 20 Feb 2014, site certified on 30 Apr 2014 | - | Download | Download |
Jul 11, 2013 | 24" Bomu - Bonny Trans Niger Pipeline at Owokiri / Bodo City | Jul 13, 2013 | Swamp | Sabotage | 16 | n/a | Spill was contained on 10 Jul 2013, recovery completed on 14 Jul 2013, assessment completed on 10 Sep 2014, clean-up and remediation completed on 23 Dec 2014, site certified on 30 Apr 2015 | - | Download | Download |
Jul 15, 2013 | 24" Bomu - Bonny Trans Niger Pipeline at Bodo City | Jul 15, 2013 | Swamp | Sabotage | 24 | n/a | Spill was contained on 14 Jul 2013, no recoverable oil found, assessment completed on 25 Aug 2015, clean-up and remediation planned for April 2019 | Site is part of the wider Bodo Project area. Currently no access to site due to community issues. Planned dates subject to change depending on grant of access. | Download | Download |
Jul 17, 2013 | 24" Bomu - Bonny Trans Niger Pipeline at Otokomabie / Oloma | Jul 18, 2013 | Swamp | Sabotage | 12 | n/a | No recoverable oil found, assessment completed on 18 Oct 2013, clean-up and remediation completed on 27 Nov 2013, site certified on 28 Feb 2014 | - | Download | Download |
Jul 23, 2013 | 12" Imo River 2 - Ogale Pipeline @ Umuololo/Owaza | Jul 24, 2013 | Land | Sabotage | 734.4 | n/a | Recovery completed on 30 Aug 2013, assessment completed on 30 Aug 2013, clean-up and remediation completed on 20 Jan 2014, site certified on 31 Jul 2014 | - | Download | Download |
Jul 24, 2013 | 12" Imo River 2 - Ogale Pipeline @ Umuedeokwara/Odagwa | Jul 25, 2013 | Land | Sabotage | 47 | n/a | Recovery completed on 03 Aug 2013, assessment completed on 14 Aug 2013, clean-up and remediation completed on 07 Oct 2013, site certified on 22 Nov 2013 | - | Download | Download |
Jul 24, 2013 | 12" Imo River - Ogale Trunkline @ Owaza | Jul 26, 2013 | Land | Sabotage | 0.8 | n/a | No recoverable oil found, assessment completed on 16 Aug 2013, clean-up and remediation completed on 04 Dec 2013, site certified on 28 Feb 2014 | - | Download | Download |
Jul 25, 2013 | 20” Otumara – Escravos D/L at Otumara | Jul 29, 2013 | Swamp | Sabotage | 5 | n/a | Spill was contained on 24 Jul 2013, recovery completed on 04 Aug 2013, assessment completed on 16 Jan 2014, clean-up and remediation completed on 16 Jan 2014, site certified on 29 Jan 2014 | - | Download | Download |
Jul 27, 2013 | 28" Bomu Bonny Pipeline at Freetown | Jul 28, 2013 | Swamp | Sabotage | 196 | n/a | Spill was contained on 26 Jul 2013, recovery completed on 14 Aug 2013, assessment completed on 17 Jan 2014, clean-up and remediation completed on 03 Apr 2014, site certified on 06 Jun 2014 | - | Download | Download |
Jul 29, 2013 | Imo River 5L Flowline at Igiriukwu | Aug 01, 2013 | Land | Sabotage | 10 | n/a | No recoverable oil found, assessment completed on 06 Sep 2013, clean-up and remediation completed on 28 Nov 2014, site certified on 28 Nov 2014 | - | Download | Download |
Jul 30, 2013 | Imo River 3 Well55S Flowline at Igiriukwu | Jul 31, 2013 | Land | Sabotage | 5 | n/a | Spill was contained on 29 Jul 2013, recovery completed on 15 Aug 2013, assessment completed on 12 Sep 2013, clean-up and remediation completed on 19 Mar 2014, site certified on 26 May 2014 | - | Download | Download |
Jul 31, 2013 | 6" Cawthorne Channel3 Well4S at Krakrama | Aug 01, 2013 | Swamp | Sabotage | 3 | n/a | Spill was contained on 30 Jul 2013, recovery completed on 11 Aug 2013, assessment completed on 06 Nov 2013, clean-up and remediation completed on 07 Feb 2014, site certified on 26 May 2014 | - | Download | Download |