November 2013
Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Recovered Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
Nov 02, 2013 14" Okordia - Rumuekpe TL at Ikarama Nov 06, 2013 Land Sabotage 101 n/a Recovery completed on 12 Dec 2013, assessment completed on 07 Jan 2014, clean-up and remediation completed on 26 Feb 2014, site certified on 28 Apr 2014 - Download Download
Nov 03, 2013 24" Nkpoku to Bomu Trans Niger Pipeline at Kpite Nov 07, 2013 Land Sabotage 10 n/a Spill was contained on 07 Nov 2013, recovery completed on 08 Nov 2013, assessment completed on 02 Dec 2013, clean-up and remediation completed on 07 Apr 2014, site certified on 28 Apr 2014 - Download Download
Nov 04, 2013 28" Nkpoku to Bomu Pipeline at Gio Nov 05, 2013 Land Sabotage 67 n/a Spill was contained on 05 Nov 2013, recovery completed on 18 Nov 2013, assessment completed on 02 Dec 2013, clean-up and remediation completed on 25 Apr 2014, site certified on 11 Jun 2014 - Download Download
Nov 06, 2013 24" Bomu to Bonny Pipeline at Kpor/K-Dere Nov 10, 2013 Land Sabotage 399 n/a Spill was contained on 08 Nov 2013, recovery completed on 04 Dec 2013, assessment completed on 26 Jan 2017, clean-up and remediation completed on 02 Jun 2018, site certification planned to be completed in Jul 2025 As a result of constant re-pollution of the site by artisanal refining and crude oil theft activities it was agreed that the Hydrocarbon Pollution Remediation Project (HYPREP) will manage the site as part of their wider Ogoniland remediation. The site will be handed over to HYPREP upon commencement of their swamp remediation programs. Download Download
Nov 06, 2013 28" Bomu to Bonny Trans Niger Pipeline at Bodo City Nov 09, 2013 Land Sabotage 48 n/a Spill was contained on 08 Nov 2013, recovery completed on 10 Nov 2013, assessment completed on 21 Aug 2015, clean-up and remediation planned for November 2018 Site assessment carried out under the Bodo Shorelines Cleanup Assessment Techniques (SCAT) project Download Download
Nov 09, 2013 28" Bomu to Bonny Pipeline at B-Dere Nov 11, 2013 Land Sabotage 12 n/a Spill was contained on 08 Nov 2013, recovery completed on 11 Nov 2013, assessment completed on 05 Dec 2013, clean-up and remediation completed on 23 Mar 2014, site certified on 28 Apr 2014 - Download Download
Nov 10, 2013 Imo River Well 21 L Flowline at Igiriukwu / Esi-Etitioha Nov 13, 2013 Land Sabotage 7 n/a No recoverable oil found, assessment completed on 27 Nov 2013, clean-up and remediation completed on 06 May 2014, site certified on 12 Sep 2014 - Download Download
Nov 12, 2013 6" Obigbo North - Ogale Pipeline at Ogale Nov 14, 2013 Land Sabotage 315 n/a Spill was contained on 13 Nov 2013, recovery completed on 28 Nov 2013, assessment completed on 13 Mar 2014, clean-up and remediation completed on 15 Apr 2014, site certified on 30 May 2014 - Download Download
Nov 18, 2013 24" Nkpoku - Bomu Trans Niger Pipeline at Egbalor Nov 19, 2013 Land Sabotage 15 n/a Recovery completed on 20 Nov 2013, assessment completed on 06 Dec 2013, clean-up and remediation completed on 19 Apr 2014, site certified on 30 May 2014 - Download Download
Nov 19, 2013 14" Okordia - Rumuekpe Trans Niger ipeline at Imogu Nov 26, 2013 Land Sabotage 210 n/a Recovery completed on 25 Apr 2014, assessment completed on 25 Apr 2014, clean-up and remediation completed on 03 Jul 2014, site certified on 30 Sep 2014 - Download Download
Nov 19, 2013 24" Nkpoku - Bomu Trans Niger Pipeline at Eteo Nov 20, 2013 Swamp Sabotage 5 n/a No recoverable oil found, assessment completed on 12 Dec 2013, clean-up and remediation completed on 13 Mar 2014, site certified on 19 Sep 2014 - Download Download
Nov 21, 2013 28" Bomu - Bonny Pipeline at Kpor/K-Dere Nov 24, 2013 Swamp Sabotage 332 n/a Spill was contained on 23 Nov 2013, recovery completed on 03 Dec 2013, assessment completed on 03 Dec 2013, clean-up and remediation completed on 09 Jul 2014, site certification planned for June 2015 - Download Download
Nov 22, 2013 Elelenwo Well 9LS wellhead at Elelenwo Dec 10, 2013 Land Operational 7 n/a Recovery completed on 22 Nov 2013, assessment completed on 07 Jan 2014, clean-up and remediation completed on 10 Oct 2014, site certified on 30 Jan 2015 - Download Download
Nov 28, 2013 28" Nkpoku to Bomu Pipeline at Gio Nov 29, 2013 Land Sabotage 97 n/a Spill was contained on 29 Nov 2013, recovery completed on 12 Dec 2013, assessment completed on 10 Mar 2014, clean-up and remediation completed on 25 Apr 2014, site certified on 11 Jun 2014 - Download Download
Nov 28, 2013 20'' Opukushi - Brass Creek Trunkline at Tamogbene Nov 30, 2013 Swamp Sabotage 72 n/a Spill was contained on 01 Dec 2013, recovery completed on 24 Dec 2013, assessment completed on 14 Mar 2014, clean-up and remediation completed on 29 Aug 2014, site certified on 19 Jan 2015 - Download Download
Nov 29, 2013 14" Okordia - Rumuekpe Pipeline @ Akaramini Dec 03, 2013 Land Sabotage 16 n/a Recovery completed on 10 Dec 2013, assessment completed on 10 Dec 2013, clean-up and remediation completed on 22 May 2014, site certified on 31 Jul 2014 - Download Download