May 2014
Date Reported Incident Site JIV Date Terrain Cause Estimated Spill Volume (bbl) Clean-up Status Comments Photo JIV Report
02.05.2014 Benisede - Akono Well-1S flowline at Ojobo 08.05.2014 Swamp Operational 14 Spill was contained on 30 Apr 2014, no recoverable oil found, assessment completed on 13 Jun 2014, clean-up and remediation completed on 23 Aug 2014, site certified on 30 Sep 2014 - Download Download
05.05.2014 8" Mininta - Rumuekpe Bulkline at Rumuekpe 07.05.2014 Land Sabotage 6 Spill was contained on 05 Apr 2014, no recoverable oil found, assessment completed on 10 Jun 2014, clean-up and remediation completed on 13 Jan 2015, site certified on 18 May 2015 - Download Download
07.05.2014 Yokri Well head-79 at Sokebolou 09.05.2014 Swamp Sabotage 607 Spill was contained on 09 May 2014, recovery completed on 24 Jun 2014, assessment completed on 25 Jun 2014, clean-up and remediation completed on 15 Aug 2014, site certified on 10 Jun 2015 Initial volume of spill estimated during the JIV of 7th May 2014 was 266 bbls. However, 364 bbls of oil was subsequently recovered, resulting in a restated volume of 607 bbls. This has been communicated to the regulators. Cleanup of residual impacted area planned for completion in June 2015. Download Download
09.05.2014 28" Nkpoku - Bomu Pipeline at B-Dere 21.05.2014 Land Sabotage 4 Spill was contained on 21 May 2014, no recoverable oil found, assessment completed on 30 Jun 2014, clean-up and remediation completed on 30 Jul 2014, site certified on 30 Aug 2014 - Download Download
10.05.2014 28" Nkpoku - Bomu Trans Niger Pipeline at B-Dere 13.05.2014 Land Sabotage 29 Spill was contained on 11 May 2014, recovery completed on 13 May 2014, assessment completed on 01 Jul 2014, clean-up and remediation completed on 15 Jul 2014, site certified on 30 Aug 2014 - Download Download
10.05.2014 Otumara Well - 22L Flowline at Ugboegungun 19.05.2014 Swamp Operational 2 No recoverable oil found, assessment completed on 11 Jun 2014, clean-up and remediation completed on 09 Jun 2015, site certified on 09 Jun 2015 - Download Download
19.05.2014 24" Nkpoku - Bomu Trans Niger Pipeline at Biara 20.05.2014 Land Sabotage 1 Spill was contained on 20 May 2014, no recoverable oil found, assessment completed on 20 May 2014, clean-up and remediation completed on 24 Aug 2014, site certified on 29 Oct 2014 - Download Download
19.05.2014 Diebu Creek Flow Station at Peremabiri 20.05.2014 Water Operational 0.3 Spill was contained on 18 May 2014, no recoverable oil found, assessment completed on 13 Jun 2014, clean-up and remediation completed on 06 Feb 2015, site certified on 21 May 2015 - Download Download
21.05.2014 28" Nkpoku - Bomu Pipeline at Ekporo 21.05.2014 Land Sabotage 657 Recovery completed on 03 Jun 2014, assessment completed on 07 Jul 2014, clean-up and remediation completed on 02 Dec 2014, site certified on 30 Jun 2015 - Download Download
21.05.2014 28" Nkpoku - Bomu Pipeline at Ekporo 21.05.2014 Land Sabotage 157 Recovery completed on 23 May 2014, assessment completed on 03 Jul 2014, clean-up and remediation completed on 02 Dec 2014, site certification planned for December 2016 - Download Download
22.05.2014 Soku Well 21S/L Well Head Slot at Russia 28.05.2014 Swamp Sabotage 0.7 No recoverable oil found, assessment completed on 19 Jun 2014, clean-up and remediation completed on 02 Oct 2014, site certified on 30 Jan 2015 - Download Download
23.05.2014 Soku Well 48L Well Head Slot at Russia 28.05.2014 Swamp Sabotage 0.7 Spill was contained on 22 May 2014, no recoverable oil found, assessment completed on 19 Jun 2014, clean-up and remediation completed on 02 Oct 2014, site certified on 30 Jan 2015 - Download Download
23.05.2014 10" Diebu Creek Pipeline at Oporoma 25.05.2014 Land Sabotage 251 Recovery completed on 18 Jun 2014, assessment completed on 18 Jun 2014, clean-up and remediation completed on 28 Apr 2015, site certified on 25 May 2015 - Download Download
31.05.2014 28'' Bomu-Bonny Pipeline at Bodo-City 01.06.2014 Land Sabotage 3 No recoverable oil found, assessment completed on 27 Aug 2014, clean-up and remediation planned for March 2017 - Download Download